Brief Minutes from a Weekly meeting on alignment

Monday 28 June '99 (1:30 - 2:30 pm)
Present:   D. Eartly  (Fermilab)
J.Moromisato (Northeastern)
R. Loveless, S. Lusin (Wisconsin)
 
    (1) Description of the start of ISR co-ordinate layouts for EMU, possible sensor configuration, goals as listed

    (2) Description of SLM prototype towers and mounts- drawings review and status      PSL construction , needed funds  from NEU for extended continued design work and prototyping

    (3) EDMS description, discussion of Simulgeo C++ libraries-system/account issues

    (4) Getting EPROMS for DCOPS/NEU replacement

    (5) Description of Pakistan beamsplitter sensor prototype proposal
     

    The next meeting  is planned at 13:30 - 14:30 on 7/8/99 (Thursday)

agenda itesms are:

(1) Progress on rad tests for DCOPS

(2) ISR layout-sensor proposals-readout configuration

(3) Full SLM test proposal in the USA before ISR

(4) Software Updates

minutes by D. Eartly
Last update date:  July 6th, 1999