After some discussion, following decision is made:
We will
go ahead with the Minnesota sensor development provided following
conditions are
met and milestones are agreed by the relevant parties.
conditions:
a) David Eartly is taking charge
to follow-up on this effort.
b) NE is paying 4K (order of 4K)
to Minnesota for the development.
c) Teresa agrees to do the testing
with the existing electronics.
milestones:
1)
Sept. 1st: Glass is purchased by Minnesota
2)
Oct. 1st: prototype is done, sent and in-hand of
Teresa by Minnesota
Oct. 1st: Teresa knows how to bond/test
3)
Nov. 1st: prototype should be bonded
4)
Dec. 5th: Test done, result available by Teresa et. al
by CMS week.
(2) Since Eric Cowden is going away, Sergei
is willing to spend a next week or so
to find out where
DCOP software is.